Piping It construction Piping It banner
Nav top
Piping It logo Spacer
Home
online planning
construction
The Facts
Events
Media
Employment
Real People, Real Stories
Pipline Unit
Land Liason
Milestones
Resources
Contract/Tender
Local Government
Contact Us
Nav bottom
Spacer  
Construction

As construction continues, GWMWater will update this section with information and photographs that illustrate the different types of construction activities for the project.

Supply System 1 – Construction of this section of the pipeline is complete (1,385km pipe, 4 sets of lined earthen storages and 3 towns provided with tank storages, ten pump stations). GWMWater operations group are now managing this section of the pipeline, with supply of Lake Bellfield water to all towns and farms within the supply zone.

Supply System 2 – Construction will be completed by the end of 2008. All pipes are ‘in the ground’, works are continuing on new pump stations and storages, and meter installation is progressing well. Emergency water is available to some customers, as meters are installed.

Supply Systems 3 & 4 – Construction commenced in May 2008, with 615 kilometres installed in Supply System 3 (Birchip). Supply System 4 (Wycheproof) trunk works have commenced near Rupanyup. Land Liaison visits to all landowners are finalising tapping point locations.

Supply System 5 – The total length of pipe has now been installed - 826 kilometres. There are 5 pump stations and 3 new balancing storages. GWMWater operations group are now managing this section of the pipeline, with supply of River Murray water to all towns and farms within the supply zone.

Supply System 6 – Land Liaison (individual landowner contacts) will continue through to October. Construction is targeted to commence in summer 2008/9.

Supply System 7 – Works are complete between Lake Bellfield and Taylors Lake, with 68 km of pipe installed for the transfer trunk, which is now providing water to SS1 and SS2.

Click to view a map of construction progress (updated 25 September)

 

August 2008

Lining the Warracknabeal storages   Lining the Warracknabeal storages
         
Sealing the lining      
         

June 2008

Construction of the new balancing storages at Nullawil   Finished balancing storages at Nullawil

May 2008

450mm PVC stack site at Rupanyup      
         

September 2007

Premier John Brumby & SS5 Construction Manager Brian Walker      
         

August 2007

Plough in method for poly installation near Nullwil   minimum disturbance of the topsoil and crop with plough in method
         

May 2007

John Forrest, Malcolm Turnbull & John Thwaites meet Barenji Gadjin representatives at Gross' Bridge      
         

March 2007

Clean down at Taylors Lake   Positioning the pipe
         
Steel pipe laying at Fishers road near Taylors Lake      
         

February 2007

Taylors Lake Pipes Community pipe signing in Dimboola   St Helens Rd Channel crossing St Helen's Rd Channel Crossing
         
Unloading Steel Pipes At Daswell's Bridge      
         

January 2007

Taylors Lake Pipes Steel pipes strung out at Taylors Lake   Dadswells Bridge Pipes 1016mm steel pipes stacked near Dadswells Bridge
         

December 2006

John Forrest Member for Mallee John Forrest watches a sub-contractor drill a bore hole at Ladlows Road adjacent to Horsham Transfer Station to insert 100mm PVC pipe into.   John Forrest Member for Mallee John Forrest with a Cleveland trencher, which is being used to lay the 450mm trunk pipe.
         
John Forrest Member for Mallee John Forrest with a row of 450mm trunk pipe in a paddock near Horsham aerodrome   Drilling Concrete Drilling concrete pipe beneath the railway line at Dooen.
         

November 2006

2 Supervisors

GWMWater contract supervisors on-site at Dooen.   Aerial trenching In the top left section of the photo the pipe has already been laid. Contractors are boring under the road and in the bottom right of the photo, the next section is ready to be trenched (Dooen site)
         
laying the pipe A Mitchell Water contractor in a trench with 450mm trunk pipe near Dooen.   Dad, I dug a hole, it's filling with water The Cleveland trencher digging a trench. In this photo you can see top soil on the right hand side of the trench, and the trenching material on the left.
         
Spacer
GWMWater
Spacer
Spacer Line
Grey block
 
Visit Phunkemedia Spacer
Spacer